MANTIS RFID SCAN
Workflow Diagrams
Application Flow
App Launch
↓
Login
↓
Select Project
↓
Select Workflow
↓
Fabricated Spools
- Fab In Progress
- Fab Complete (QC, RFID)
- Shipped (BOL)
- Onsite (Geo-tag)
- Install In Progress
- Install Complete
- CCO Complete
Field Run Piping
- Print Label (on-site)
- % Complete (5% inc.)
- Complete (enter LF)
- CCO Complete
Inline Devices
Instrumentation (7)
- Onsite
- Calibrated (opt.)
- Installed
- Tubing
- Electrical
- Complete
- CCO
- Onsite
- Complete (torqued)
- CCO
- Onsite
- Calibrated (opt.)
- Installed
- Tubing
- Electrical
- Complete (torqued)
- CCO
Fabricated Spools - 7 Stage Flow
1. Fab In Progress
→
2. Fab Complete
→
3. Shipped
→
4. Onsite
→
5. Installing
→
6. Installed
→
7. CCO
Stage 1: Fab In Progress
Spool ID
SP-2024-0847
Line Number
4"-STM-1234
Service
150# Steam
1
2
3
4
5
6
7
Stage 2: Fab Complete
✓ RFID Scanned
✓
100% Complete✓
Final QC Passed✓
RFID Label Applied✓
RFID ScannedStage 3: Shipped
Bill of Lading
BOL-2024-1234 [SCAN]
Carrier
[Dropdown]
Truck #
TRK-5589
Associate items to BOL
Stage 4: Onsite
Delivered
📍 Geo-Tag
31.54°N, 97.14°W
☐
SP-0847 [SCAN]✓
SP-0848☐
SP-0849 [SCAN]Stage 5: Installing
Location
Boiler House, L2
Crew
Steam Crew A
📍 Movement
Geo-stamp on scan
Stage 6: Installed
✓ Verified
Final Location
L2-B7
Installed By
J. Rodriguez
Date/Time
Jan 15, 4:22 PM
Stage 7: CCO
●
CCO Complete ✓○
Punch Item RequiredSelect one option
Field Run Piping - 4 Stage Flow
1. Print Label
→
2. % Complete
→
3. Complete
→
4. CCO
Print Label
Line Number
2"-HW-5678
Service
Hot Water Return
Estimated
150 LF
1 label per line, on-site
Progress Update
Percent Complete
45%
Select
[Dropdown] 5% increments
5%, 10%, 15%... 95%, 100%
Complete (100%)
✓ Complete
Actual LF Installed
147
Variance
-3 LF (2%)
CCO Review
Est: 150 LF
Act: 147 LF
Var: -2%
○
CCO Complete ✓○
Punch ItemInline Devices
Instrumentation (7)
FT-1234
✓
Onsite✓
Calibrated [Y/N/NA]✓
Installed (watertight)○
Tubing Installed☐
Electrical Complete☐
Complete☐
CCO Complete[SCAN] or [✓] each stage
Calibration (Optional)
Per project setting
●
Yes - Calibrated○
No - Not Required○
N/AManual Valves (3)
HV-5678
✓
Onsite○
Complete (bolts torqued)☐
CCO Complete[SCAN] or [✓] each stage
Control Valves (7)
FCV-9012
✓
Onsite✓
Calibrated [Y/N/NA]✓
Installed (watertight)✓
Tubing Installed○
Electrical Complete☐
Complete (torqued)☐
CCO Complete[SCAN] or [✓] each stage
Punch Item Flow
CCO Review
↓
Issue?
No
↓
CCO Complete ✓
Yes
↓
Punch Item Dialog
↓
Punch Open
↓
[SCAN] or [✓] Complete
↓
Punch Complete ✓
Punch Item Dialog
Issue Description *
Text input
Hours to Resolve *
[Number]
Photo Evidence *
📷 Capture
Punch Item List
PI-0023 Open
Steam trap replacement
Est: 4 hrs • 📷 1
PI-0022 ✓ Done
Insulation support
Discrepancy Report
⚠ BOL Mismatch
BOL-2024-1234
Expected:5
Received:4
Missing
SP-2024-0850
📍 Location
31.54°N, 97.14°W
Notes
Legend
[SCAN] RFID scan action (trigger or camera)
[✓] Manual completion option
📍 Geo-location capture (automatic)
📷 Photo capture required
●/○ Radio button (select one)
✓/☐ Checkbox (complete/incomplete)
[Dropdown] Selection list
→ Flow direction / next step