MANTIS RFID SCAN
Lo-Fi Wireframes • Box Layout
Workflow Diagram
App Launch
Login
Select Project
Select Workflow
Fabricated Spools
- Fab In Progress
- Fab Complete
- Shipped (BOL)
- Onsite (Geo)
- Install In Progress
- Install Complete
- CCO Complete
Field Run Piping
- Print Label
- % Complete (5%)
- Complete (LF)
- CCO Complete
Inline Devices
Instrumentation (7)
Manual Valves (3)
Control Valves (7)
- Onsite
- Calibrated
- Installed
- Tubing
- Electrical
- Complete
- CCO
Manual Valves (3)
- Onsite
- Complete
- CCO
Control Valves (7)
- Onsite
- Calibrated
- Installed
- Tubing
- Electrical
- Complete
- CCO
Core Screens
◇
MANTIS
Username
email@company.com
Password
••••••••
SIGN IN
Forgot Password?
Login
←
Select Project
Waco Paper Mill
Waco, TX • 234 items
Macon Pulp HVAC
Macon, GA • 89 items
Waco Hot Water
Waco, TX • 156 items
Project Selection
←
Waco Paper Mill
Fabricated Spools
7-stage tracking
Field Run Piping
On-site installation
Inline Devices
Valves & Instrumentation
Workflow Selection
←
Scan RFID
[ ]
Point scanner at RFID tag
or press trigger
📷 Camera
✎ Manual
Scan Ready
Fabricated Spools (7 Stages)
←
Spool Details
SP-2024-0847
Fab In Progress
Line Number
4"-STM-1234-A1
Service
150# Steam
Size
4" NPS
1
2
3
4
5
6
7
SCAN TO UPDATE
Stage 1: Fab In Progress
←
Fab Complete
✓ RFID Scanned
SP-2024-0847
Complete
Checklist
✓
100% Complete✓
Final QC Passed✓
RFID Label Applied✓
RFID Scanned✓
2
3
4
5
6
7
PROCEED TO SHIPPING →
Stage 2: Fab Complete
←
Ship Spool
SP-2024-0847
Ready to Ship
Bill of Lading #
BOL-2024-1234
◎
Carrier
Select Carrier ▼
Truck #
TRK-5589
Scanned Items (3)
SP-2024-0847
SP-2024-0848
SP-2024-0849
SCAN DEPARTURE
Stage 3: Shipped (BOL)
←
Receive Delivery
BOL-2024-1234
Delivered
📍 Geo-Tagged Location
31.5493° N, 97.1467° W
Jan 15, 2026 • 2:34 PM
Unload Verification
☐
SP-2024-0847 ◎✓
SP-2024-0848☐
SP-2024-0849 ◎⚠ REPORT DISCREPANCY
✓ CONFIRM RECEIPT
Stage 4: Onsite (Geo-tag)
←
Installation
SP-2024-0847
Installing
Location
Boiler House, Level 2
Crew
Steam Crew A
📍 Movement Tracking
2:34 PM → Pipe Yard
3:15 PM → Boiler House
✓
✓
✓
✓
5
6
7
SCAN: INSTALL COMPLETE
Stage 5: Install In Progress
←
Install Complete
✓ Installation Verified
SP-2024-0847
Installed
Final Location
Boiler House, L2-B7
Installed By
J. Rodriguez
Completed
Jan 15, 4:22 PM
✓
✓
✓
✓
✓
6
7
PROCEED TO CCO →
Stage 6: Install Complete
←
CCO Completion
SP-2024-0847
CCO Review
CCO Complete ✓
All work verified
Punch Item Required
Issue needs resolution
✓
✓
✓
✓
✓
✓
7
✓ COMPLETE CCO
Stage 7: CCO Complete
Field Run Piping
←
Field Run Piping
FR-2024-0156
New
Line Number
2"-HW-5678-B3
Service
Hot Water Return
Estimated LF
150 LF
🖨
1 label per line
🖨 PRINT RFID LABEL
◎ SCAN EXISTING
Print Label On-site
←
Update Progress
FR-2024-0156
In Progress
Percent Complete
45%
45% ▼
5% increments
SCAN TO UPDATE
Progress (5% increments)
←
Complete Line
✓ 100% Complete
FR-2024-0156
Complete
Actual Quantity Installed
147
LF
Variance:
-3 LF (2%)
✓ CONFIRM COMPLETE
Complete (Actual LF)
←
CCO Review
FR-2024-0156
CCO Review
Estimated
150 LF
Actual
147 LF
Variance
-2%
CCO Complete ✓
Punch Item
SCAN TO COMPLETE
CCO Complete
Inline Devices
←
Instrumentation
FT-1234
In Progress
✓
Onsite✓
Calibrated Yes✓
Installed (watertight)○
Tubing Installed☐
Electrical Complete☐
Complete☐
CCO CompleteSCAN NEXT STAGE
Instrumentation (7 stages)
←
Calibration
FT-1234
Calibration
Calibration Required?
Optional per project
Yes - Calibrated
No - Not Required
N/A
CONFIRM →
Calibration (Optional)
←
Manual Valve
HV-5678
In Progress
✓
Onsite ◎/✓○
Complete (Bolts Torqued) ◎/✓☐
CCO Complete ◎/✓◎ Scan
✓ Mark
Manual Valves (3 stages)
←
Control Valve
FCV-9012
In Progress
✓
Onsite✓
Calibrated✓
Installed✓
Tubing○
Electrical☐
Complete (Torqued)☐
CCO CompleteSCAN / ✓ COMPLETE
Control Valves (7 stages)
Shared Components
←
CCO
Punch Item Dialog
←
Punch Items
PI-0023
Open
Steam trap replacement
Est: 4 hrs • 📷 1 photo
◎ Scan
✓ Mark
PI-0022
✓ Done
Insulation support added
Resolved: Jan 14
Punch Item List
←
Discrepancy Report
⚠ BOL Mismatch
BOL-2024-1234
Expected
5
Received
4
Missing:
SP-2024-0850 - Not Scanned
📍 31.5493° N, 97.1467° W
Jan 15, 2:34 PM
Notes
SUBMIT REPORT
Discrepancy Report
✓
Complete!
SP-2024-0847
CCO Verified
7 of 7
Stages
0
Punch
SCAN NEXT ITEM
RETURN TO DASHBOARD
Success State
Design Notes:
- ◎ = RFID Scan action (hardware trigger or camera)
- ✓ = Manual completion option
- 📍 = Geo-location capture
- 📷 = Photo capture required
- All stages support both Scan OR Manual completion
- Calibration is optional per project configuration
- Progress tracking uses 5% increments for Field Run
- Punch items require: Issue, Hours, Photo